Noord has completed tank pit U at the Antwerp Terminal
Published by Oliver Kleinschmidt,
Assistant Editor
Tanks and Terminals,
At the Noord Natie Odfjell Antwerp Terminal (NNOAT) was able to complete their latest expansion tank pit U and have been able to fill up the first two tanks ahead of schedule.
With the addition of six new tanks, each having a capacity of 6000 m³, the total capacity added is 36 000 m3 which has boosted the sites total capacity to 461 000m³. The successful completion of the project has been owed to the hard work of all the employees and contractors involved, including Ivens, Verwater Group B.V., IBS Bouw, Agidens, and FTS Design & Construction Co.
NNOAT aims to continue expansion with work underway on a new truck loading station with the site 3 position.
Read the article online at: https://www.tanksterminals.com/terminals/16112023/noord-natie-odfjell-has-completed-tank-pit-u-at-the-antwerp-terminal/
You might also like
Hydrocarbon Engineering Podcast
Peter Davidson, CEO of the Tank Storage Association (TSA), joins us to discuss the essential role that the tank storage sector has to play in ensuring supply security and resilience, as well as in facilitating the energy transition.
Woodside awards Worley agreement extension for onshore assets in Western Australia
Worley will provide brownfield engineering and procurement services to the Karratha Gas Plant, King Bay Supply Base, and the Pluto LNG Plant.