Mabanaft participates in hearing for the construction of ammonia import terminal
Published by Poppy Clements,
Assistant Editor
Tanks and Terminals,
Mabanaft, an energy company based in Germany, has reached another milestone in the planned construction of its ammonia import terminal in the Port of Hamburg.
Mabanaft presented the necessary construction measures in an application conference before Hamburg’s Environment, Climate, Energy and Agriculture Authority (BUKEA). The construction measures include building a tank for storing liquid ammonia at Mabanaft’s existing Blumensand tank terminal in the Port of Hamburg, Germany.
In the past week, the HAZID risk analysis was conducted over several days, and was successfully completed. During this, experts, together with competent employees of the Hamburg Port Authority (HPA), examined possible nautical risks in the operation of the terminal, as well as in the arrival and departure of so-called ‘Very Large Gas Carriers’ at Mabanaft’s Blumensand tank terminal operating site.
Volker Ebeling, Senior Vice President New Energy, Chemicals and Gas, at Mabanaft, said: “The ammonia import terminal is the first step in building New Energy Gate, a terminal for sustainable hydrogen products that will enable Hamburg to import large amounts of climate-friendly energy. With the application conference in front of the BUKEA, we are getting a lot closer to this goal. We are now working flat out to open the approval process.”
In a next step, Mabanaft will submit the approval documents to BUKEA and initiate the approval process in accordance with the Federal Immission Control Act.
Read the article online at: https://www.tanksterminals.com/terminals/12072023/mabanaft-participates-in-hearing-for-the-construction-of-ammonia-import-terminal/
You might also like
Hydrocarbon Engineering Podcast
Peter Davidson, CEO of the Tank Storage Association (TSA), joins us to discuss the essential role that the tank storage sector has to play in ensuring supply security and resilience, as well as in facilitating the energy transition.
Woodside awards Worley agreement extension for onshore assets in Western Australia
Worley will provide brownfield engineering and procurement services to the Karratha Gas Plant, King Bay Supply Base, and the Pluto LNG Plant.