TGE announce the mechanical completion of LNG Receiving Terminal
Published by Oliver Kleinschmidt,
Deputy Editor
Tanks and Terminals,
TGE Gas Engineering have announced the mechanical completion of its Huizhou LNG Receiving Terminal EPC Project in Guangdong Province.
TGE reached this milestone 20 days earlier than contractually initiated. The Project, consisting of three separate 200 000 m³ LNG storage tanks plus related facilities, and enables the loading and unloading of LNG ships with sizes between 80 000 and 266 000 m³. The maximum annual capacity for receiving liquefied natural gas is 6.1 million t. It has been arranged for the terminal to be brought to operation by mid of 2024.
Read the article online at: https://www.tanksterminals.com/terminals/08022024/tge-announce-the-mechanical-completion-of-lng-receiving-terminal/
You might also like
Hydrocarbon Engineering Podcast
Peter Davidson, CEO of the Tank Storage Association (TSA), joins us to discuss the essential role that the tank storage sector has to play in ensuring supply security and resilience, as well as in facilitating the energy transition.
Argent LNG launches EPC review and pre-filing process with FERC
Argent LNG has initiated a comprehensive EPC partner review in preparation for entering the Federal Energy Regulatory Commission pre-filing and permitting process for its 25 million tpy LNG export project in Louisiana.