Final acceptance audit of Wilhelmshaven LNG terminal successful
Published by Callum O'Reilly,
Senior Editor
Tanks and Terminals,
On 28 February 2023, the final acceptance audit took place at the Wilhelmshaven LNG terminal by the responsible authorities under the leadership of the Oldenburg State Trade Supervisory Office (GAA Oldenburg).
This final acceptance is stipulated in the BImSchG approval notice (BImSchG = Federal Immission Control Act) dated 16 December 2022.
Acceptance took place without any objections.
With the successful completion of this final step, the Wilhelmshaven LNG terminal in Voslapper Groden, Germany, commenced regular operations as of 1 March 2023.
The facility was built by Uniper in record time and became the first German LNG import terminal to start operations on 21 December 2022, initially in trial operation. Since then, one LNG tanker has been unloaded every week and the LNG is regasified at the Höegh Esperanza FSRU and injected into the natural gas grid from there.
It is currently the only LNG import terminal that contributes reliably and with significant volumes of natural gas to the security of supply in Germany. Around 6% of Germany's gas demand can be met via the terminal. Uniper, as the installer and operator of the terminal, will continue to play a key role in ensuring that there are no gas shortages in Germany in the future, especially in the coming winter of 2023/24.
Since the start of commercial operation on 15 January 2023, the federal government company, Deutsche Energy Terminal GmbH (DET), has assumed the role of plant operator and permit holder. LNG Terminal Wilhelmshaven GmbH (LTeW) has taken over the task of technical and commercial management of the LNG terminal on behalf of DET.
Read the article online at: https://www.tanksterminals.com/terminals/03032023/final-acceptance-audit-of-wilhelmshaven-lng-terminal-successful/
You might also like
Hydrocarbon Engineering Podcast
Peter Davidson, CEO of the Tank Storage Association (TSA), joins us to discuss the essential role that the tank storage sector has to play in ensuring supply security and resilience, as well as in facilitating the energy transition.
Woodside awards Worley agreement extension for onshore assets in Western Australia
Worley will provide brownfield engineering and procurement services to the Karratha Gas Plant, King Bay Supply Base, and the Pluto LNG Plant.